FHA/HUD | 2026-11-27

HUD Construction Draws Need a 15-Day Funding Checklist

Current HUD-92441M links each draw to advance notice, verified work and stored materials, retainage, source sequencing, lien control, and updated title coverage.

HUD's current forms page identifies HUD-92441M, Building Loan Agreement, for transactions with firm commitments issued on or after April 1, 2026. The form bars the lender from advancing loan funds until the borrower and lender have submitted the documents required by the agreement and Firm Commitment and HUD has completed the Note's initial endorsement. After that gate, the borrower applies monthly on HUD-92403 for insured advances.

For construction items, the requested amount starts with the value of work acceptably completed, adds materials and equipment delivered and suitably stored on-site, and adds off-site components that comply with Program Obligations. The calculation then subtracts the 10-percent holdback, subject to any approved Retainage Reduction Rider, and prior advances. Each application must be filed at least 15 days before the desired advance date, and the borrower is entitled only to the amount approved by the lender and, as Program Obligations require, HUD.

The draw also depends on source and lien controls. Project Completion Funds generally must be advanced before loan proceeds unless Program Obligations and the approved disbursement agreement provide otherwise, and the borrower holds each advance in trust for the approved items. Before the first advance, the borrower must deliver a current certified survey and satisfactory title evidence; the title coverage must extend to every advance when paid and show no mechanics' or materialmen's liens. The lender may require lien releases through each draw and with final payment.

A practical draw tracker should identify the desired funding date, 15-day submission deadline, HUD-92403 version, completed-work value, on-site and off-site stored materials, holdback, prior advances, Project Completion Funds balance, loan-proceeds amount, source order, survey status, title endorsement, lien search and releases, lender approval, HUD approval, and wire evidence. Reconcile the approved requisition to the cost breakdown, disbursement agreement, title update, and actual payment before releasing funds. This note is informational only and is not legal advice for any specific transaction.